Area manager Interview Questions in Canada

4K

Area Manager interview questions shared by candidates

Top Interview Questions

Sort: Relevance|Popular|Date
Amazon
Area Manager was asked...March 11, 2011

Math Question: Inbound Flow Question: You are in charge of the department that receives the product in to the building and stows it to the bin where it is accessible by the department. you have two options on how to receive and stow the product. In the first option, you receive the product at 250 units per labor hour and stow it at 100 units per labor hour. You must receive it and stow it for the unit to count for production. This process results in 1% of the units stowed being incorrect. You can find and fix these errors at a rate of 20 units for labor hour with what you believe is almost 100% accuracy. In the second option, you receive and stow the product in one step vs. two. The rate for this process is 80 units per labor hours for receive and stow. This process results in 1.5% of the units being stowed being incorrect. You can find and fix these errors at a rate of 20 units per hour with what you believe is almost 100% accuracy. 1. Which option would you select to process today's units and why? 2. Does your answer change if you are told you must fully process 100,000 units today? If yes, why? 3. Does your answer change if you are told that you have 15 associates today and you must fully produce the maximum amount of units possible? If yes, why?

20 Answers

I like the top answer, but it's a bit complex.....lets make this simple. Start with a setting a production goal at a number that is easy to work with. Lets say 1,000 Units. In option A it would take 4 Labor hours to receive 1,000 units (1,000/250=4) and it would take 10 labor hours to stow 1,000 units 1,000/100=10). 1,000 units X the error rate of .01 = 10 errors. Since you can correct 20 errors in an hour it would take .5 hours to correct the 10 mistakes. So for Option A it would take a total of 14.5 hours (4+10+.5=14.5) to receive and stow 1,000 units. In option B you can receive and stow at a rate of 80 units per hour. So 1,000/80 = 12.5 hours. There is a error rate of 1.5% using this method. So 1000 X .015 = 15 errors. Since we can correct 20 mistakes per hour it would take .75 hours to correct the mistakes. The total hours to receive and stow 1,000 units using this option at 13.25 hours (12.5+.75=13.25). Option B is the best method. Option B will always be the better method, unless we are given new or updated data. I hope this helps. Less

1st scenario: Assumption - we have 1000 units To receive 1000 units, we would need 4hrs (@250units/hr) and to stow 1000 units, we need 10 hrs (@100 units/hr). # stowed incorrectly @1% = 10 and it takes 0.5 hrs to correct it. So total hrs is14.5 hrs (4+10+.5). Scenario 2: To receive and stow 1000 units, we need 12.5 hrs (@80units/hr). # stowed incorrectly @1.5% is 15 and it would take 0.75 hrs to correct it. Total time = 13.25 hrs (12.5+.75) So option 2 is better in this scenario. Doing the same math for 100000 units, Option 1 takes 1450 hrs and option 2 takes 1325 hrs. So Option 2 is always better, I guess!!! Less

Please don't let this question confuse you. Option 1 produces about 69 units per hour whereas option 2 produces about 76 per hour. The answer is so much more simple than everyone is making it out to be. In any situation option 2 is going to give you more units per hour which is more productive. The are no special factors or tricks. Option 2. Pause and act like you're doing the math to avoid undue embarrassment. Less

Show More Responses
Amazon

Tell me about yourself. Don't say something typical

16 Answers

Yo solo quiero estar llevando acabó actividad, que beneficien tanto inversión, clientes y trabajadores Less

Define , Typical then I will proceed with my answers. 4 days a week in my sleep I feel I have superman abilities and fly over sea with no passport. Rest of the week I sleep sound.. Less

Hardworking, empathetic, and self-aware leader.

Show More Responses
Amazon

Math Problem: You have an upstream Picking department that feeds two downstream packing departments: A and B. 75% of your Pick volume goes to department A, which has a packing rate of 150 unites per labor hour (uph). 25% of the Pick volume goes to department B, which is for large items, and has a pack rate of 25 units per labor hour. Your pickers pick both large and small items throughout the day at an overall average rate of 100 units per labor hour. You have 25 people today for all 3 departments, and you absolutely must pack 7,500 units in department A to meet a customer promise metric. How do you allocate labor to balance the flow in your department if you work a 10 hour shift? Do not assume breaks or lunches in your answer. Department % of volume Rate (uph) People Daily Volume Pick 100% 100 ?? ?? Pack A 75% 150 ?? 7,500 Pack B 25% 25 ?? ??

10 Answers

Pick 10 people × 100 uph × 10 hours = 10000 units Pack A 5 people × 150 uph × 10 hours = 7500 units. Pack B 10 people × 25 uph × 10 hours = 2500 units . Less

7500 units for A so 2500 units for B (25%)=10000 units 10000 units at 100 uph/10 hrs=10 pickers 7500 units/10 hrs/150 up =5 packers A 2500 units/10 hrs/25 uph =10 packers B Less

xxxxx

Show More Responses
Amazon

Phone screening Math Flow question: You have 30 associates, 2 are not on the production floor. Each can process 150 UPH; Each works 8 hr days, 5 days week; each day each worker is given 2 15 min breaks. How many units can they output per week?

14 Answers

I got 157,500 units

My answer came out to be 157,500 for the week of working 5 days 7.5 hrs/day... with 150 units per hour and 28 AAs. Less

so how was the question ? the answer is 157.500 not 137,500

Show More Responses
Amazon

They asked about earning trust and diving deep to finish a project etc

12 Answers

ग्xXxfxxxxxxxxZZZzzZzZzzzzzzzzzzzzzzzXzzZZZZZZzzzzZzZzzzzzzzzZzzzzzzzZZ

dxdddddddddddddddddd,,,,,,,,,

b

Show More Responses
Amazon
Area Manager was asked...September 17, 2009

You have 25 laborers for a shift. Pickers pick 100 units an hour Small item packers pack 150 units an hour Large item packers pack 25 units an hour You must pack 7500 small units during a ten hour shift. How would you staff your shift?

9 Answers

You gave a single answer... Right answer? sure. Right response? no. 25 Workers (breaks up nicely with 5 laborer unit ratios): A) 3:2 Pickers to Small Item Packers B) 1:4 Pickers to Large Item Packers C) 2:1:2 Pickers to Small item Packers to Pickers 5 Small item packers are required. Any combination of A, B and C where the number of small item packers >= 5. Candidate's response: 5*C (A valid answer only meeting the minimum demand for small items) Why would the candidate's answer be better than 5*A? 15 Pickers 15,000 units/shift 10 Small item Packers 15,000 units/shift Why would the candidate's answer be better than 2*A + 3*C? 12 Pickers 12,000 units/shift 7 Small item Packers 10,500 units/shift 6 Large item Packers 1,500 units/shift Why would the candidate's answer be better than 3*A + 2*B? 11 Pickers 11,000 units/shift 6 Small item Packers 9,000 units/shift 8 Large item Packers 2,000 units/shift ^--If they asked for a single solution, I'd argue this one would be better since you buffered the small item output. Less

Maximizing your daily output is not necessarily the way to go. You have customers waiting for orders and if you work on mostly smalls, the amount of large units in your backlog will be high. So while your numbers look good, you may not being getting orders out to customers timley. This question would make more sense if it said how many units have been ordered of small and large items so you can be sure to get through the orders in a FIFO basis. Less

25 laborers for shift. Picker are packing 125 units of large items. Small item are packing 175 units. Each laborer does 12 units each producing 300 units. The 300 units produce by the 25 laborers Will produce 7500. Less

Show More Responses
Cogelec
Area Manager was asked...February 22, 2019

Nothing that sparks to mind. Did all the talking. Sales manager knew nothing about sales techniques and had to explain what a "proof of concept" is.

9 Answers

n/a

JAime

Electeicieb

Show More Responses
Amazon

Math Problem will be emailed. Then you will be required to explain it. Please take 15 minutes to review this question and be prepared to present your answer to the panel. You have an upstream Picking department that feeds two downstream packing departments: A and B. 75% of your Pick volume goes to department A, which has a packing rate of 150 units per labor hour (uph). 25% of the Pick volume goes to department B, which is for large items, and has a pack rate of 25 units per labor hour. Your pickers pick both large and small items throughout the day at an overall average rate of 100 units per labor hour. You have 25 people today for all 3 departments, and you absolutely must pack 7500 units in department A to meet a customer promise metric. How do you allocate labor to balance the flow in your department if you work a 10 hour shift? Do not assume breaks or lunches in your answer. Department % of volume Rate (uph) People Daily volume Pick 100% 100 ?? ?? Pack A 75% 150 ?? 7500 Pack B 25% 25 ?? ?? My solution. Overall Volume * 75% = 7500 *.75 = 7500 = 7500/.75 Overall Volume = 10,000 = uph * hours * people = 100 * 10 * people = 1000 10 = people Packing A: 7,500 = uph * hours * people = 150 * 10 * people = 1500 7500 / 1500 = people 5 = people Packing B: 10,000 * 25% = 2500 2500 = uph * hours * people = 25 * 10 * people 2500 = 250 * people 10 = people Now cut uph on Packing Department A: from 150 to 125. How much volume is packed during the first 5 hours? How much volume is packed during the second 5 hours on Packing Department A? Your must meet the 10,000 overall volume and 75000 (Pack A) From which department do you move people? What is the overall output for each department after move?

7 Answers

Nevermind over looked the 125 part

6 ppl at PACK A 10 ppl at PACK B Would leave you with 9 People for Picking which = 9,000 units picked for the day. Which would create a shortage for total units packed. No? Less

Part 2: with 125uph in A, 7500/125 = 60; Labour hours = 60 Labor hours/10 working hours = 6 Labors Volume of units packed in first 5 hours = 125 Units/Labor hour * 5 hours * 6 Labors (or simply 7500/2); Therefore, Volume of units packed in first 5 hours = 3750 Units Pick:9 (JPH raised to 111 jph because of the balancing) Pack A: 6 Pack B: 5 Output of Pick: 10000 Output of A: 7500 Output of B: 2500 Less

Show More Responses
Amazon

1. You have a team of 30, they get 2x 15 min breaks a day, 2 people can't work the floor each day, each person processes 150 units and hour. how many units processed in 1 week

6 Answers

Ummm— why would you use 7 days??? Especially if working 10 hour shifts... answer should be 159,600 (28 * 9.5) = 266 * 150 units = 39,900 * 4 (days at 10 hrs each)= 159,600 Less

assuming 10 hour day 279300 28 employees times 9.5 hours (10 minus two 15 min breaks = 9.5 hours) times 150 times 7 so basically 28 employees x 9.5 hours x 150 units per hour x 7 days = 279300 units per week Less

Without knowing how many hours employees work a day, you won't be able to solve the problem. You can only guess and give answer for 8 or 10 hour day. Less

Show More Responses
Swiggy

You have have 2 Delivery guys and 3 orders in different route. executive need to pick orders from different hotel but only one at a time. how do you manage the time so that orders are delivered in minimum time

6 Answers

Answer

Distance to restaurant Distance to customer from restaurant Preparation time for the order All three variables should be considered and assign executives accordingly Less

Depend off people

Show More Responses
Viewing 1 - 10 of 4,273 Interview Questions